Thursday, 8 December 2011

leveling hill

  1. we first put on our boots because we had to go through the brick work shop.
  2. we then got the tools needed (level, tripod and measuring staff).
  3. we then put the level out side and set it up making sure it is in level.
  4. once it was all set up one person had to read the measurement through the scope while another had to hold the measuring staff up right their were also another person that would take down the measurements.
  5. once we had all the measurements then we had to put it in to a graph we done this by taking one result from the other.
  6. once we had done every think we then had to make sure every thing was clean and had been put back in the right place.
  7. finally we reported that the job were done. 